Our Projects

American data center layout——327MW

Georgia project: 31MW
Electrified in May 2022

Macon, Georgia
31MW / 9,000 machine seats
National Grid
$11.6 million
Georgia Power, RTP Pricing, 
5 Years
lease

Indiana project: 71MW
Electrified 21MW in June 2022

Marion, Indiana area
21MW / 6,800 seats + 50MW 
expandable load
Nuclear Power
$6 million
Michigan Power of Indiana
own

Texas project: 50 MW-10 MW
Electrified 10MW in March 2022

Texas
10MW / 3,000 seats + 40MW 
expandable load
Grid
$2.55 million
own

Wyoming project: 75MW
Electrified 45MW in March 2023

Cheyenne, Wyoming
45MW / 14,000 & 30MW / 5,640 
machine seats
National Grid
$30 million
Black Hill Energy, BCIS pricing, 5 years
own

West Texas project: 50MW
Expected by July 2023

Cheyenne, Wyoming
45MW / 14,000 & 30MW / 5,640 
machine seats
National Grid
$30 million
Black Hill Energy, BCIS pricing, 5 years
own